Refreshing migrations

Migrator::refresh() rolls back every applied migration through its own down(), then runs every migration again through up(), as one operation under one lock.

use Dirthara\Migration\Config\MigrationConfiguration;

$migrator->refresh(new MigrationConfiguration(['database/migrations']));
ArgumentTypeDefaultMeaning
configurationMigrationConfigurationnoneThe migration directories and the locking choice of the run.

Refresh is meant for development: checking that a set of migrations goes down and up again cleanly, or rebuilding a database from migrations whose down() you trust. To rebuild without running any down(), use fresh migrations instead.

What a refresh does​

  1. Takes the migration lock, unless locking is turned off.
  2. Loads the migrations of every directory into one set, checks the set, and resolves the connection every migration declares.
  3. Creates the history table when it does not exist, and selects every applied migration, latest applied first.
  4. Plans the rollback of all of them, as a rollback would.
  5. Reverses them one by one: beforeDown(), down(), afterDown().
  6. When the history is empty, runs every migration again, as migrate() would: beforeUp(), up(), afterUp().
  7. Releases the lock.

The rollback phase​

The rollback phase reverses every applied migration, ignoring batches, in the opposite order to the one they were applied in. It follows the history, as a rollback does: each down() runs on the connection the history recorded, not on the one the migration would resolve to today.

Everything is planned before the first down() runs. A migration whose source is missing, whose index changed, whose declared connection no longer matches the history, or whose recorded connection cannot be resolved fails the refresh before anything is rolled back. The connection every migration would run on in the forward phase is resolved at the same time, so a pending migration naming a connection that does not exist also stops the refresh before it starts.

The forward phase​

Once every migration has been rolled back, the history is empty, and the migrations run again exactly as a first migrate() would: per connection, by index, each on the connection it resolves to now. The history is written anew, and every migration is recorded in batch 1, whatever batches it was in before.

An incomplete rollback​

caution

Refresh only starts the forward phase when the rollback phase reversed every applied migration.

Rollback hooks are honoured. When beforeDown() skips a migration, the rollback moves on to the next one; when it stops, the rollback ends. Either way, migrations are still applied, and running every migration again on top of them would not be a refresh. The refresh therefore throws a Dirthara\Migration\Exception\MigrationRefreshException without running any migration again. Its migrations context lists the migrations that are still applied, in the order they were applied. What was rolled back stays rolled back.

A migration that throws in beforeDown(), down(), or afterDown() ends the refresh the same way a failing rollback does: the migration is recorded in the history again, its exception reaches the caller unchanged, and no migration runs again.

A failure in the forward phase behaves as it does in migrate(). The migrations that ran before it stay applied in batch 1.

note

A refresh is not atomic. When it fails partway, the database holds what the phases completed before the failure. Fix the cause, then migrate, or refresh again.

Locking​

One migration lock covers the whole refresh, from planning the rollback to recording the last migration it runs again. It is not released between the phases, so no other runner can migrate or roll back in between. The refresh respects the same locking option as a run.